Quarterly Report January To March, Laikipia North Sub County

  0  

The period under review was generally dry for the first and second months however there were moderate rainfall across the entire sub county with Mukogodo forest areas have slightly more rainfall than the other areas toward the end third of the quarter . The rainfall have replenished most of the water bodies, while seasonal river commonly known as (laggas) where sub surface dams are were replenished the rains are expected continue into the following month however there were no damages reported in any of the water facilities.

Below are activities that were done within the period

s/no Project name Achievements Outstanding /remarks
1 Bokish borehole Borehole drilled to 150m Pump testing done yield 2.2m3/hr Equipping with solar pump and pipeline distribution system
2 Katonga borehole Drilled bh depth 80 m Pump testing done yield 2m3/hr equipping with solar ,storage Tank and distribution piping system
3 Tangi Nyeusi borehole Cleaning done up to 135m BQ for pipe work done – Trenching in progress Pipeline laying and communal water points installation of sub mersible solar pumps Pipe laying Construction of 3no yard taps
4 Musul dam Work on the rehabilitation of this dam was started mid this month and is ongoing Site super had challenges in order to get the rehabilitation quantum’s
5 Imotiok borehole Drilling contractor identified and ready to move to site Drilling works not yet Solar pump installation Pipeline laying Communal water points construction Survey and design
6 Doldol water supply The ongoing work by WSTF is progressing well and was monitored by wstf official from their HQs on27/3/2018 Accompanying measures Action on snag list
7 Murupusi wind pump Rehabilitation done Replacement grand parking The water supply is now operational Communal water point tap and cattle trough require minor repairs

 