Water And Natural Resources Scorecard Laikipia East Sub County
The following has been achieved during the period under review. The major activities were on repairs of boreholes that had broken down that had caused water shortage in the respective areas. A total of 8No boreholes have been repaired and are fully operational.
-
Mutirithia handpump in Segera ward. Serves Mutirithia primary school and the local community
-
Naibor solar pump in Segera ward was repaired and currently operational
-
Marura handpump in Nanyuki ward repaired. Serves a health center and the local community
-
Burugutia handpump in Nanyuki ward repaired and is operational. It serves a primary school and local wanaichi
-
Munyaka windmill in Ngibit ward. Serves the local community within the b/h area
-
Mukuri handpump in Nanyuki was repaired and is operational
-
Kiamukie handpump in Umande ward repaired and is operational
-
Muramati Tetu handpump was repaired and currently operational
WATER SCHEMES
Major works were done on 2NO Water supply schemes in Laikipia east sub county to increase the coverage.
-
Tigithigi water project located in Tigithi ward.
- Construction of lockable manholes
- installation of washouts along the pipelines
- installation of airvalves and valve chambers
2. Solio water project
- completion of designs and drawings and bills of quantities
- repair of pipelines
3. kiamaringa water Project- Procurement of materials for extension of pipeline in progress
4. Nturukuma, Nkando and Jikaze water projects in Nanyuki ward – procurement of required materials for rehabilitation both rising mains and reticulation pipelines in progress.
5. Nyambongishi water project in Ngobit Ward- procurement for materials to carry out pipelines extension in progress.
WATER PANS. 3No water pans estimated at storage capacity of 10,000M3 each were rehabilitated in Laikipia East subcounty. Estimated cost was Ksh2.8M per pan to do desilting, repair of embarkment, spillway, fabricating branding & erecting sign post and reinstate the site.
-
Kalalu pan located in Umande ward. Rehabilitation works complete and operational
-
Mirera pan in Nanyuki Ward.- Rehabilitation complete. Currently operation
-
Imenye pan in Ngobit
-
Solio pan in Tigithi ward completed and operational
Enforce Equitable Sharing of Water Resources and Protect Water Sources from Pollution.
-
No achievements during the period.