The following has been achieved in Laikipia west the during period.
Dams & Pans
-
Longomot dam in Marmanet ward completed and serving local community.
-
Gatarasha pan in Githiga ward currently ongoing
-
Karungubee dam in Olmoran fully completed and operational.
-
Leporos Pan in Rumuruti ward fully complete completed and operational.
-
Mahianyu Pan in Ingwamiti ward is currently ongoing
COMPLETED/ONGOING BOREHOLES
-
Gathanji in sosian ward drilled and capped.
-
Matuiku in Githiga ward
-
Tandare b/h repaired. Laying of pipeline of 6km complete. Auxiliary works ongoing.
-
Salama in salama ward repaired. Primary school and local community are served by the b/h
-
Wagwachi repaired and is operational
-
Olmoran in Olmoran ward repaired and serving the community
-
Mahinga repaired and fully operational
-
Karungubee repauired and is operational
-
Dimcon repaired and operational
-
Mithuri repaired and currently operational
-
Kiambogo repaired and currently operational. Serves a primary school and local community.
-
Thome repaired and operational
-
Gikoni repaired and is operational
-
Sipili B/H. This was a WSTF and CGL Partnership project. county contributed 3M towards procurement and installation of submersible pump and transformer. All works complete and is operational.
-
Ngaremare borehole was drilled and capped. Awaiting equipping. Procurement process is in progress
-
Kauka drilled and capped. Procurement of all equipping items in progress viz:- pumping unit, pipes and pipefittings, construction materials for small civil works.